Daily reports
A daily report is the project's record of one day. Your organization writes down what happened on site that day. Each activity points at a construction-stage task, and often at a unit (e.g. wind turbine). Cost, progress, and Records of Event all read this same report, so the site does not type the day three times.
Activities are classed as work schedule (planned work), extra work, or standby. On the screen these types are called Work Schedule, Extra work, and Stand by. Extra work can be caused by an unexpected situation. Parts may arrive dirty and need cleaning, or paint may be damaged and need painting. No access can also cause extra work. That cause can be logged as a deviation, and the extra work can be linked to it. Standby is used when people or equipment wait. For example, a crane and its crew can be on standby for a whole week while the crane is broken or weather is bad.
Daily Reports in the top menu opens the list of reports for the project that is currently selected.
Who writes and who reviews
You create one report per day for each organization role you work in. Usually a subcontractor writes its report and the project owner reviews it. The project owner can accept the report, or reject it so the subcontractor can correct it. Which organization reviews whom is set on Organizations permissions. There, the organization that sends the report is called previous in reporting flow, and the one that reviews it is next in reporting flow.
Accepting matters later. Cost overviews follow accepted reports. Activities that were not accepted, and their cost, stay out of project overviews until the matter is resolved.
The life of a report
- Create the report for a day and an organization role. The status shown on the new report is
IN PROGRESS. That means the report is still being filled in. See Daily reports list. - Fill it in. Add activities, expenses, weather, and attachments. See Details and Create and edit activity.
- Submit it. The status changes to
PENDING. That means the report has been submitted and is waiting for review. The report can no longer be edited. A report with no activity and no expense cannot be submitted. A subcontractor then accepts the lines on the report and clicks Accept. The report has to be accepted, fully or in part, before they can forward it. They then click Forward to and the project owner's name. The project owner can review the report only after that. See Daily report. - Review. The reviewing organization ticks each activity and each expense it accepts. It then clicks Accept or Reject. If every line was ticked, Accept changes the status to
ACCEPTED. The report is then fully accepted. If some lines were left unticked, Accept changes the status toPARTLY ACCEPTED. Those lines still need to be resolved. Reject changes the status toREOPENED. The organization that wrote the report can then correct it. - Correct if needed. While the status is
PENDINGorREOPENED, the organization that wrote the report can click Edit. The status changes back toIN PROGRESS. The report can be changed, and then submitted again.
Submit does not save your work. Your entries are already saved. Submit locks the report for editing. The project owner can review it only after the subcontractor forwards it.
Permissions
Your organization role assignments and these permissions decide what you see and can do. The permission names are the ones shown under Show my permissions; see Where I can find my permissions in SUM-IT.
View all reportslets you see the reported data of every organization role assigned to your organization. It also covers organizations that granted "Review reported data" to your organization.View reports for assigned organization rolelets you see only the reports of the organization roles you are assigned to. It is part ofView all reports, and is switched on automatically with it. With this narrower permission, Deviation details, Project overview, Dashboard, and Project Summary also stay limited to your organization roles.Createlets you create reports. It also lets you add activities, weather, and attachments to a report of your organization that isIN PROGRESS.Edit report detailslets you change any item on your organization's reports.Edit own report detailslets you change only the items you created.Delete report detailsandDelete own report detailswork the same way for deleting.Submitlets you submit a report.Accept daily reportandReject daily reportlet you accept or reject a report that your organization reviews.
In this section
- Daily reports list — Find a report and create a new one.
- Daily report — The report for one day: status, submit, accept or reject, change the date, export, weather, and copy to other days.
- Details — The day's activities, accepting lines, comments, and expenses.
- Create and edit activity — Type, task, unit, and the people and equipment with their hours.
- Attachments — Files for the day's report.
- Timeline — The hours of each person and machine as bars, and adjusting them.
- Time-it — Turning Time-it time logs into activities.